Observation Deck update

Observation deck update:
"We did have a delay in the progress of the hanglider deck due to an injury of my lead carpenter on that project, To date the structural framing members are installed and the deck boards are getting installed along with the guard rail posts. I have assigned a new lead carpenter to the project and we are on schedule to have the project completed by the end of June"
"We did have a delay in the progress of the hanglider deck due to an injury of my lead carpenter on that project, To date the structural framing members are installed and the deck boards are getting installed along with the guard rail posts. I have assigned a new lead carpenter to the project and we are on schedule to have the project completed by the end of June"